Safety failures, not misfortune, caused crane collapse that killed 31

Safety failures, not misfortune, caused crane collapse that killed 31 | Thaiger
Safety failures, not misfortune, caused crane collapse that killed 31Legacy

Safety failures, not misfortune, caused crane collapse that killed 31 | Thaiger

A construction crane collapse, causing a train crash in Thailand that killed 31, has been ruled the result of procedural violations and safety failures rather than an unavoidable accident, according to findings released by a government fact-finding committee on May 26.

Thirty-one people died when equipment from a high-speed rail construction site fell onto Express Train No. 21, operating between Krung Thep Aphiwat Central Terminal and Ubon Ratchathani, at 9.15am on January 14, between Nong Nam Khun and Si Khio stations in Nakhon Ratchasima province.

The findings were presented jointly by Jirapong Theppithak, Deputy Permanent Secretary of the Ministry of Transport and chairman of the fact-finding committee, alongside Piyapong Jiwatthanakun Phokkun, Director-General of the Department of Highways, and Anan Photnimdaeng, acting governor of the State Railway of Thailand (SRT).

Jirapong said the committee conducted a 45-day investigation that included site inspections, destructive and non-destructive materials testing, electron microscope analysis of metal components, structural collapse modelling, and interviews with all relevant parties, including the contractor, construction supervisor, project owner, and railway station staff.

Fact-finding commitee announces the investigation results of the Thailand train crash in January, 2026
Fact-finding committee announces the investigation results | Photo via Amarin

Investigation findings

The committee determined that the accident resulted from a combination of failures in operational procedure, safety controls, and site supervision. The launching gantry, a large crane used to lift and install precast concrete segments, was operated in breach of engineering procedures and safety requirements on the day of the incident.

The front support point was overloaded as a result, causing structural failure and the collapse of the equipment onto the active rail line as the train passed.

Specific lapses identified by the committee included failure to obtain a formal window time authorisation to suspend train operations before work began, work being carried out prior to official approval, and equipment inspections that fell outside the required schedule.

On-site supervision was also found to be inconsistent with the standards required under the project’s guidelines.

The committee recommended strengthening the oversight system for construction projects within active rail corridors, including deploying an appropriate number of engineering personnel, increasing the rigour of on-site monitoring, and improving joint safety inspection mechanisms with external agencies.

Safety failures, not misfortune, caused crane collapse that killed 31 | News by Thaiger
Scene of the crane collapse | Photo via Facebook/ กรมป้องกันและบรรเทาสาธารณภัย DDPM

Anan confirmed that the SRT’s own investigation board had submitted its findings to the Ministry of Transport, and that contractual and legal processes in relation to those findings were underway. Construction work on the project was continuing under tightened supervision and safety controls, he said.

Safety measures announced

The SRT announced a series of measures to be implemented across all projects nationwide. All work near railway boundaries will require written window time authorisation from the SRT before any activity on overhead structures can begin.

The existing system of advance and retrospective work approvals will be abolished, replaced by daily approvals from the construction supervision consultant, supported by photographic evidence taken on site before sign-off.

Engineers and safety officers must be present throughout all working periods. Any activity found to be non-compliant with safety standards will result in an immediate work stoppage with no exceptions.

All launching gantry cranes currently in use across projects will undergo independent third-party inspection covering structural systems, lifting systems, and hydraulics. PT Bar anchor bolts will be replaced after no more than 60 operational cycles and may not be reused under any circumstances.

Real-time monitoring equipment is also to be installed on all machinery, including inclination sensors, tension sensors, and CCTV cameras, enabling immediate work stoppages when anomalies are detected.

Contractor selection criteria for high-risk projects will be revised to place greater weight on specialist experience and safety standards alongside price, and penalties for safety non-compliance under contract terms will be strengthened.

Anan said the SRT was compiling a full assessment of damage to infrastructure, assets, and rail operations to support contractual and legal proceedings against those responsible. He said the process would be handled transparently, fairly, and with public safety as the primary consideration.

Rescuers at the scene of the accident
Photo via Facebook/ Fire & Rescue Thailand

The story Safety failures, not misfortune, caused crane collapse that killed 31 as seen on Thaiger News.

About admin